Request History Viewer
Milestones
Request # CT06903

DateDescriptionAdditional Details
12/13/2018 10:03:10 AMRequest opened by Reader, CTWR 
12/13/2018 8:25:27 AMRequest opened by Reader, CTWR 
5/6/2018 10:34:50 PMRequest opened by Reader, CTWR 
9/21/2016 7:22:29 AMRequest opened by Gromak, Stephen 
6/23/2016 9:34:53 AMRequest opened by Gromak, Stephen 
5/5/2016 6:35:49 AMRequest opened by Reader, CTWR 
5/5/2016 6:35:36 AMRequest opened by Reader, CTWR 
5/5/2016 12:36:03 AMRequest opened by Reader, CTWR 
5/3/2016 12:24:09 PMRequest opened by Nurnberger, Jim 
5/3/2016 12:24:05 PMRequest opened by Nurnberger, Jim 
5/3/2016 12:06:59 PMRequest opened by Gromak, Stephen 
5/3/2016 12:06:58 PMRequest CT06903 Cycles to Completion 
5/3/2016 12:06:58 PMPart 12668130-F Cycles to Completion 
5/3/2016 12:06:57 PMPart 12668130-F ApprovedApproved by Gromak, Stephen
5/3/2016 12:06:50 PMRequest opened by Gromak, Stephen 
5/3/2016 12:04:06 PMRequest opened by Gromak, Stephen 
5/3/2016 11:14:57 AMRequest opened by Nurnberger, Jim 
5/3/2016 11:14:57 AMWork Item completed by by Nurnberger, Jim 
5/3/2016 11:14:28 AMRequest opened by Nurnberger, Jim 
5/3/2016 11:13:59 AMRequest opened by Nurnberger, Jim 
5/3/2016 10:13:01 AMRequest opened by Nurnberger, Jim 
5/3/2016 10:12:56 AMRequest opened by Nurnberger, Jim 
5/2/2016 12:33:25 PMRequest opened by Nurnberger, Jim 
5/2/2016 12:33:25 PMDC assignment by Nurnberger, Jim 
5/2/2016 12:33:03 PMRequest opened by Nurnberger, Jim 
5/2/2016 12:32:58 PMRequest opened by Nurnberger, Jim 
4/19/2016 1:09:32 PMRequest opened by Reader, CTWR 
3/29/2016 8:24:08 AMRequest opened by Nurnberger, Jim 
3/29/2016 6:30:00 AMRequest opened by Hilvers, Kurt 
3/24/2016 12:07:58 PMRequest opened by Bujouves, Jim 
3/24/2016 12:04:14 PMRequest opened by Bujouves, Jim 
3/24/2016 12:03:29 PMRequest opened by Bujouves, Jim 
3/24/2016 12:01:41 PMRequest opened by Bujouves, Jim 
3/24/2016 11:26:29 AMRequest opened by Bujouves, Jim 
3/24/2016 10:52:53 AMRequest opened by Buss.D, Dave 
3/24/2016 7:11:25 AMRequest opened by Bujouves, Jim 
3/24/2016 7:11:25 AMAll TMs have approved the request 
3/24/2016 7:11:25 AMTM approval by Bujouves, Jim 
3/24/2016 7:11:10 AMRequest opened by Bujouves, Jim 
3/24/2016 7:03:21 AMRequest submitted by Gromak, Stephen, no PTE review required 
3/24/2016 7:03:21 AMAll PTEs have acknowledged the request 
3/24/2016 6:42:38 AMRequest opened by Gromak, Stephen 
3/24/2016 6:42:21 AMRequest opened by Bujouves, Jim 
3/24/2016 6:42:21 AMTM rework requested by Bujouves, JimThe reason for rework request was: Rework for RH ansd LH please.
3/24/2016 6:29:28 AMRequest opened by Bujouves, Jim 
3/24/2016 5:59:45 AMRequest submitted by Gromak, Stephen, no PTE review required 
3/24/2016 5:59:44 AMAll PTEs have acknowledged the request 
3/24/2016 5:49:11 AMRequest saved by Gromak, Stephen 
3/24/2016 5:35:47 AMRequest opened by Gromak, Stephen 
3/24/2016 5:35:46 AMRequest created by Gromak, Stephen