DateDescriptionAdditional Details
12/13/2018 9:58:40 AMRequest opened by Reader, CTWR 
12/13/2018 9:16:17 AMRequest opened by Reader, CTWR 
12/13/2018 8:20:58 AMRequest opened by Reader, CTWR 
10/30/2018 9:12:39 AMRequest opened by Sorg, Chris 
10/30/2018 9:12:02 AMRequest opened by Sorg, Chris 
10/30/2018 9:12:01 AMRequest CT08106 Cycles to Completion 
10/30/2018 9:12:01 AMPart 12671855 Cycles to Completion 
10/30/2018 9:12:01 AMPart 12671855 ApprovedApproved by Sorg, Chris
10/30/2018 9:11:45 AMRequest opened by Sorg, Chris 
10/30/2018 9:11:35 AMRequest opened by Sorg, Chris 
7/24/2018 7:23:57 PMRequest opened by Reader, CTWR 
5/6/2018 10:30:50 PMRequest opened by Reader, CTWR 
4/24/2018 3:17:19 PMRequest opened by Reader, CTWR 
3/2/2018 8:09:00 AMRequest opened by Fasbinder, Anthony 
3/2/2018 8:09:00 AMWork Item completed by by Fasbinder, Anthony 
3/2/2018 8:07:57 AMRequest opened by Fasbinder, Anthony 
3/2/2018 8:07:47 AMRequest opened by Fasbinder, Anthony 
2/27/2018 10:55:42 AMRequest opened by Luszczynski, James 
2/27/2018 10:55:41 AMDC assignment by Luszczynski, James 
2/27/2018 10:55:30 AMRequest opened by Luszczynski, James 
2/27/2018 10:55:25 AMRequest opened by Luszczynski, James 
2/27/2018 10:55:24 AMAll TMs have approved the request 
2/27/2018 10:55:24 AMTM approval by Luszczynski, James 
2/27/2018 10:54:43 AMRequest opened by Luszczynski, James 
2/27/2018 8:51:54 AMRequest opened by Keys, John 
2/27/2018 2:29:11 AMRequest opened by Reader, CTWR 
2/26/2018 1:06:43 PMRequest submitted by Sorg, Chris, no PTE review required 
2/26/2018 1:06:43 PMAll PTEs have acknowledged the request 
2/26/2018 1:04:28 PMRequest opened by Sorg, Chris 
2/26/2018 1:04:28 PMRequest created by Sorg, Chris