| 10/30/2018 9:11:28 AM | Request CT08105 Cycles to Completion | |
| 10/30/2018 9:11:28 AM | Part 12671855 Cycles to Completion | |
| 10/30/2018 9:11:27 AM | Part 12671855 Approved | Approved by Sorg, Chris |
| 10/30/2018 9:11:26 AM | Part 12671855 Approved | Approved by Sorg, Chris |
| 3/2/2018 8:07:36 AM | Work Item completed by by Fasbinder, Anthony | |
| 3/2/2018 8:07:15 AM | Work Item completed by by Fasbinder, Anthony | |
| 2/27/2018 10:56:46 AM | DC assignment by Luszczynski, James | |
| 2/27/2018 10:56:39 AM | DC assignment by Luszczynski, James | |
| 2/27/2018 10:56:20 AM | All TMs have approved the request | |
| 2/27/2018 10:56:20 AM | TM approval by Luszczynski, James | |
| 2/26/2018 9:44:45 AM | Request submitted by Sorg, Chris, no PTE review required | |
| 2/26/2018 9:44:45 AM | All PTEs have acknowledged the request | |
| 2/26/2018 9:38:38 AM | Request created by Sorg, Chris | |