| 7/20/2018 2:06:45 PM | Request CT08315 Cycles to Completion | |
| 7/20/2018 2:06:44 PM | Part 12691253-F Cycles to Completion | |
| 7/20/2018 2:06:44 PM | Part 12691253-F Approved | Approved by Hesterman, Wesley |
| 7/20/2018 2:06:41 PM | Work Item completed by by Hesterman, Wesley | |
| 7/20/2018 2:06:29 PM | Part 12691253-F Approved | Approved by Hesterman, Wesley |
| 7/20/2018 2:06:25 PM | Work Item completed by by Hesterman, Wesley | |
| 7/16/2018 7:22:50 AM | DC assignment by Laker, Andrew | |
| 7/2/2018 9:11:17 AM | All TMs have approved the request | |
| 7/2/2018 9:11:17 AM | TM approval by Hilvers, Kurt | |
| 6/28/2018 3:16:39 PM | Request submitted by Hesterman, Wesley, no PTE review required | |
| 6/28/2018 3:16:39 PM | All PTEs have acknowledged the request | |
| 6/28/2018 3:12:08 PM | Request created by Hesterman, Wesley | |