| 12/10/2018 3:48:50 PM | Request CT08479 Cycles to Completion | |
| 12/10/2018 3:48:50 PM | Part 84094549 Cycles to Completion | |
| 12/10/2018 3:48:49 PM | Part 84094549 Approved | Approved by Appold, Brian |
| 12/7/2018 5:55:09 AM | Work Item completed by by Adcock, Jill | |
| 12/6/2018 3:20:34 PM | PTE item rework requested by Appold, Brian | Part=84094549, Component=Mold Base Assembly - Deck, Item=Select. The reason for rework request was: "No ppt attached" |
| 11/16/2018 6:12:42 AM | Work Item completed by by Adcock, Jill | |
| 11/16/2018 6:12:10 AM | DC assignment by Adcock, Jill | |
| 11/9/2018 2:42:32 PM | All TMs have approved the request | |
| 11/9/2018 2:42:32 PM | TM approval by Hilvers, Kurt | |
| 11/8/2018 4:33:18 PM | Request submitted by Appold, Brian, no PTE review required | |
| 11/8/2018 4:33:18 PM | All PTEs have acknowledged the request | |
| 11/8/2018 4:28:30 PM | Request created by Appold, Brian | |