Work Approval Matrix Request # CT05437

Primary Part: HFV6  HEAD  12647554  Prod  Saginaw Status: Complete - Approved
View / Edit Tooling Component List

Core Box - Cavity & Support Items
Core Stick Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
8/13/2013 9:46:37 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  I Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 10/3/2013 9:31:55 AM Request Rework Review Date: 10/7/2013 12:14:51 PM
  ECO: CT05437-12647554-022-AG   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)10/3/2013 9:23:46 AM
Submit Attachment: File:   Description:   Add

Insert Assembly - Lower Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
8/13/2013 9:46:23 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  I Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 10/3/2013 9:31:44 AM Request Rework Review Date: 10/7/2013 12:14:56 PM
  ECO: CT05437-12647554-022-AG   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)10/3/2013 9:24:31 AM
Submit Attachment: File:   Description:   Add

Metal Stick - Riser or Gate Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
8/13/2013 9:46:08 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  I Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 10/3/2013 9:31:31 AM Request Rework Review Date: 10/7/2013 12:15:06 PM
  ECO: CT05437-12647554-022-AG   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)10/3/2013 9:24:50 AM
Submit Attachment: File:   Description:   Add

SPM - Molding & Support Items
Mold Base Assembly - Deck Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
8/13/2013 9:45:55 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 10/3/2013 9:31:17 AM Request Rework Review Date: 10/7/2013 12:15:12 PM
  ECO: CT05437-12647554-022-AG   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)10/3/2013 9:25:02 AM
Submit Attachment: File:   Description:   Add