Work Approval Matrix Request # CT05583

Primary Part: GEN V  HEAD  12629344  Prod  Bedford Status: Complete - Approved
View / Edit Tooling Component List

SPM - Molding & Support Items
Bridge Assembly - Opposite Pour Side Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Adcock, Jill ( fzl662 )
11/4/2013 1:58:37 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Adcock, Jill ( fzl662 ) Approve PTE Name: Buss, Dave ( lzclfb )
Completion Date: 11/5/2013 8:00:49 AM Request Rework Review Date: 11/5/2013 1:19:32 PM
  ECO: CT05583-12629344-1-026   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete pipeAdcock, Jill (fzl662)11/5/2013 7:59:50 AM
Submit Attachment: File:   Description:   Add

Bridge Assembly - Pour Side Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Adcock, Jill ( fzl662 )
11/4/2013 1:58:47 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Adcock, Jill ( fzl662 ) Approve PTE Name: Buss, Dave ( lzclfb )
Completion Date: 11/5/2013 8:00:56 AM Request Rework Review Date: 11/5/2013 1:19:42 PM
  ECO: CT05583-12629344-1-026   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete pipeAdcock, Jill (fzl662)11/5/2013 8:00:00 AM
Submit Attachment: File:   Description:   Add

Impacted Part: GEN V  HEAD  12620214  Prod  Bedford Status: Complete - Approved
View / Edit Tooling Component List

SPM - Molding & Support Items
Bridge Assembly - Opposite Pour Side Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Adcock, Jill ( fzl662 )
11/4/2013 1:58:59 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Adcock, Jill ( fzl662 ) Approve PTE Name: Buss, Dave ( lzclfb )
Completion Date: 11/5/2013 8:01:12 AM Request Rework Review Date: 11/5/2013 1:19:49 PM
  ECO: CT05583-12620214-1-026   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete pipeAdcock, Jill (fzl662)11/5/2013 8:00:15 AM
Submit Attachment: File:   Description:   Add

Bridge Assembly - Pour Side Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Adcock, Jill ( fzl662 )
11/4/2013 1:59:09 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Adcock, Jill ( fzl662 ) Approve PTE Name: Buss, Dave ( lzclfb )
Completion Date: 11/5/2013 8:01:21 AM Request Rework Review Date: 11/5/2013 1:20:01 PM
  ECO: CT05583-12620214-1-026   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete pipeAdcock, Jill (fzl662)11/5/2013 8:00:25 AM
Submit Attachment: File:   Description:   Add