Work Approval Matrix Request # CT06597

Primary Part: GF6 FWD CONV  HOUSING  24262946  Prod  Bedford Status: Complete - Approved
View / Edit Tooling Component List

Cavity & Support Items
Process Model - Bottom Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Goller, Jon ( mz2lx9 )
10/14/2015 11:40:13 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Goller, Jon ( mz2lx9 ) Approve PTE Name: Goller, Jon ( mz2lx9 )
Completion Date: 2/29/2016 10:15:24 AM Request Rework Review Date: 1/29/2018 11:57:08 AM
  ECO: CT06597-24262946-065   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete ECL-LUGoller, Jon (mz2lx9)2/29/2016 10:10:59 AM
Submit Attachment: File:   Description:   Add

Process Model - Cover Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Goller, Jon ( mz2lx9 )
10/14/2015 11:40:27 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Goller, Jon ( mz2lx9 ) Approve PTE Name: Goller, Jon ( mz2lx9 )
Completion Date: 2/29/2016 10:15:31 AM Request Rework Review Date: 1/29/2018 11:57:13 AM
  ECO: CT06597-24262946-065   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete ECL-LUGoller, Jon (mz2lx9)2/29/2016 10:11:21 AM
Submit Attachment: File:   Description:   Add

Process Model - Ejector Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Goller, Jon ( mz2lx9 )
10/14/2015 11:43:46 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Goller, Jon ( mz2lx9 ) Approve PTE Name: Goller, Jon ( mz2lx9 )
Completion Date: 2/29/2016 10:15:41 AM Request Rework Review Date: 1/29/2018 11:57:18 AM
  ECO: CT06597-24262946-065   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete ECL-LUGoller, Jon (mz2lx9)2/29/2016 10:12:02 AM
Submit Attachment: File:   Description:   Add

Process Model - Helper Side Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Goller, Jon ( mz2lx9 )
10/14/2015 11:44:01 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Goller, Jon ( mz2lx9 ) Approve PTE Name: Goller, Jon ( mz2lx9 )
Completion Date: 2/29/2016 10:15:53 AM Request Rework Review Date: 1/29/2018 11:57:24 AM
  ECO: CT06597-24262946-065   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete ECL-LUGoller, Jon (mz2lx9)2/29/2016 10:12:35 AM
Submit Attachment: File:   Description:   Add

Process Model - Operator Side Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Goller, Jon ( mz2lx9 )
10/14/2015 11:44:15 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Goller, Jon ( mz2lx9 ) Approve PTE Name: Goller, Jon ( mz2lx9 )
Completion Date: 2/29/2016 10:16:04 AM Request Rework Review Date: 1/29/2018 11:57:30 AM
  ECO: CT06597-24262946-065   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete ECL-LUGoller, Jon (mz2lx9)2/29/2016 10:13:31 AM
Submit Attachment: File:   Description:   Add

Process Model - Top Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Goller, Jon ( mz2lx9 )
10/14/2015 11:44:39 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Goller, Jon ( mz2lx9 ) Approve PTE Name: Goller, Jon ( mz2lx9 )
Completion Date: 2/29/2016 10:16:19 AM Request Rework Review Date: 1/29/2018 11:57:36 AM
  ECO: CT06597-24262946-065   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete ECL-LUGoller, Jon (mz2lx9)2/29/2016 10:14:30 AM
Submit Attachment: File:   Description:   Add