Work Approval Matrix Request # CT08145

Primary Part: HFV6  HEAD  12647554  Prod  Saginaw Status: Complete - Approved
View / Edit Tooling Component List

Core Box - Cavity & Support Items
Core Stick Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
3/23/2018 9:41:35 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  E Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 3/28/2018 6:47:41 AM Request Rework Review Date: 3/28/2018 7:31:11 AM
  ECO: CT08145-12647554-022   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)3/28/2018 6:46:31 AM
Submit Attachment: File:   Description:   Add

Insert Assembly - Lower Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
3/23/2018 9:41:28 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  E Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 3/28/2018 6:47:32 AM Request Rework Review Date: 3/28/2018 7:31:13 AM
  ECO: CT08145-12647554-022   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)3/28/2018 6:46:22 AM
Submit Attachment: File:   Description:   Add

Impacted Part: HFV6  HEAD  12647555  Prod  Saginaw Status: Complete - Approved
View / Edit Tooling Component List

Core Box - Cavity & Support Items
Core Stick Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
3/23/2018 9:41:19 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  E Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 3/28/2018 6:48:14 AM Request Rework Review Date: 3/28/2018 7:30:58 AM
  ECO: CT08145-12647555-022   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)3/28/2018 6:46:12 AM
Submit Attachment: File:   Description:   Add

Insert Assembly - Lower Effort:  Major
Design Coordinator PL Name:
Assigned Date:
Status:
Nurnberger, Jim ( zzq5yj )
3/23/2018 9:41:11 AM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  E Cancel Complete PL Name: Nurnberger, Jim ( zzq5yj ) Approve PTE Name: Waters, Russ ( hzskw3 )
Completion Date: 3/28/2018 6:48:06 AM Request Rework Review Date: 3/28/2018 7:31:01 AM
  ECO: CT08145-12647555-022   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete POWERPOINTNurnberger, Jim (zzq5yj)3/28/2018 6:46:00 AM
Submit Attachment: File:   Description:   Add