Work Approval Matrix Request # CT08175

Primary Part: GEN V  HEAD  12620214  Prod  Bedford 1 Status: Complete - Approved
View / Edit Tooling Component List

SPM - Molding & Support Items
Mold Slide Assembly - Exhaust Slide Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Geer, Tommy ( pzh3mm )
4/12/2018 4:55:15 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Geer, Tommy ( pzh3mm ) Approve PTE Name: Geer, Tommy ( pzh3mm )
Completion Date: 4/12/2018 5:09:43 PM Request Rework Review Date: 4/12/2018 5:09:48 PM
  ECO: CT08175   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete Completed PowerPointGeer, Tommy (pzh3mm)4/12/2018 5:08:38 PM
Submit Attachment: File:   Description:   Add

Mold Slide Assembly - Intake Slide Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Geer, Tommy ( pzh3mm )
4/12/2018 4:55:20 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Geer, Tommy ( pzh3mm ) Approve PTE Name: Geer, Tommy ( pzh3mm )
Completion Date: 4/12/2018 5:09:46 PM Request Rework Review Date: 4/12/2018 5:09:50 PM
  ECO: CT08175   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete Completed PowerPointGeer, Tommy (pzh3mm)4/12/2018 5:08:46 PM
Submit Attachment: File:   Description:   Add

Impacted Part: GEN V  HEAD  12629344  Prod  Bedford 1 Status: Complete - Approved
View / Edit Tooling Component List

SPM - Molding & Support Items
Mold Slide Assembly - Exhaust Slide Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Geer, Tommy ( pzh3mm )
4/12/2018 4:55:27 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Geer, Tommy ( pzh3mm ) Approve PTE Name: Geer, Tommy ( pzh3mm )
Completion Date: 4/12/2018 5:09:58 PM Request Rework Review Date: 4/12/2018 5:10:05 PM
  ECO: CT08175   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete Completed PowerPointGeer, Tommy (pzh3mm)4/12/2018 5:09:28 PM
Submit Attachment: File:   Description:   Add

Mold Slide Assembly - Intake Slide Effort:  Minor
Design Coordinator PL Name:
Assigned Date:
Status:
Geer, Tommy ( pzh3mm )
4/12/2018 4:55:35 PM
Complete - Approved
Assign Project Leader
  Item Design Coordinator Project Leader PTE Approval
  Select Cancel Complete PL Name: Geer, Tommy ( pzh3mm ) Approve PTE Name: Geer, Tommy ( pzh3mm )
Completion Date: 4/12/2018 5:10:01 PM Request Rework Review Date: 4/12/2018 5:10:08 PM
  ECO: CT08175   Status: Complete - Approved
 
 File NameDescriptionUser NameUpload Date
Delete Completed PowerPointGeer, Tommy (pzh3mm)4/12/2018 5:09:35 PM
Submit Attachment: File:   Description:   Add